Thursday, January 8, 2009

Now is the time to buy

The reason I say that it because I ordered a new wind turbine for a customer in the Thumb about 4 weeks ago and they tell me it will be another 8 weeks before it arrives. So here are a few more reasons to buy now.
1. Submit paperwork to your zoning official for approval, 2 weeks
2. Submitting the net-metering agreement for the power companies approval, 2- 3 weeks
3. Once you have the zoning permit, building permit is submitted, 1-2 weeks
4. Once all the first two are approved order new turbine, 8-10 weeks
5. Do all these items now, ready to have installed by the time the snow is gone.

On average it takes 8 - 10 weeks to even start installing that new wind turbine on your property.

So call for an appointment to get yours installed as soon as Spring is here.

For those of you that look at Wunderground to find out what the weather is at the Flynn project, that weather station is down. I need to climb up the tv tower and change the batteries in the weather vane. I will also be moving that weather station to the thumb and install my weather station that I have here at my office on the Flynn project, beause the one here is solar powered.